BALIKESIR POTABLE WATER TREATMENT PLANT AND
PUMPING STATIONS
Type Of Contract: Design Build Contract with 1 year
operation supervision
Position Hold: Project Coordinator
Average Flow: 220.000 m3/day
Max. Flow: 229.800 m3/day
Process Units: P0 Raw Water Pumping Station,
Cascade Aeration, Flash Mixing, Injection Mixing,
Flocculation Mixing, Lamella Sedimentation (Actiflo), Micro
Sand Recirculation, Mixing Chamber, Rapid Sand Filtration,
Contact Tank, Treated Water Tank, Backwash Water
Recovery, Thickener, Filter Press, Reagent Building,
Transformer Stations, P1 Treated Water Pumping Station,
P2 Treated Water Pumping Station
PURSAKLAR POTABLE WATER TREATMENT PLANT
Type Of Contract: Design Build Contract with 1 year
operation supervision
Position Hold: Project Manager
Average Flow: 75.000 m3/day
Max. Flow: 90.000 m3/day
Process Units: Raw Water Regulation, Flash
Mixing, Flocculation Mixing, Lamella Sedimentation
(Multiflo), Rapid Sand Filtration, Contact Tank, Treated
Water Tank, Backwash Water Recovery, Reagent Building,
Transformer Station,
KAYAS BAYINDIR POTABLE WATER TREATMENT PLANT
Type Of Contract: Design Build Contract with 1 year
operation supervision
Position Hold: Project Manager
Average Flow: 30.000 m3/day
Max. Flow: 31.200 m3/day
Process Units: Raw Water Pumping Station, Flash
Mixing, Flocculation Mixing, Lamella Sedimentation
(Multiflo), Rapid Sand Filtration, Contact Tank, Treated
Water Tank, Backwash Water Recovery, Reagent Building,
Transformer Station,
MERSIN POTABLE WATER TREATMENT PLANT
Type Of Contract: Design Build Contract with 1 year
operation supervision
Position Hold: Project Manager
Average Flow: 390.000 m3/day (3 Stage – 130.000
m3/day each stage)
Process Units: Raw Water Pumping Station,
Cascade Aeration, Flash Mixing, Sedimentation Unit
(Cyclofloc), Micro Sand Recirculation, Rapid Sand Filtration,
Contact Tank, Treated Water Tank, Backwash Water
Recovery, Thickener, Filter Press, Reagent Building, Chlorine
Building, Transformer Station,