2- TRANSPORTATION PROJECTS
HARAMAIN HIGH SPEED RAILWAY PROJECT – MADINAH
STATION
Type Of Contract: FIDIC Red Book
Position Hold: OM, Training, Handover
Coordinator, Coordination
Of Works, Management
Consultancy
Track: 450 km
Design Speed: 360 km/h
Train Capacity: 535 passenger/train
Number of Carriages: 16
HHR System Stations: 5 Stations
Madinah Station Buildup Area: 172.000 m2
Madinah Station Capacity: 1608 passanger/hour
Madinah Station Composed of: Main Building, Arrival &
Departure Concourses, Terminals (6 track platform), Mosque
(600 worshipers), Fire Station, Helipad, Short Term & Long
Term Car Park for 1000 vehicles, Lounges, Retail Areas
NORTH – SOUTH RAILWAY PROJECT NARIYAH WORKSHOP
WORKS
Type Of Contract: FIDIC Red Book
Position Hold: Test & Commissioning Team Leader,
Taking Over Coordinator,
Coordination Of Works
Nariyah Workshop Works Composed of:
Locomotive Maintenance Shop, Yard Facility, Fuelling System,
Fuelling System-Fuel Pump Room, Fuelling System-Oil Lab,
Fuelling System-Compressor Room, 4 Generator Rooms, 3
Mechanical Service Block, Track & Signal Maintenance Gangs,
Wagon Maintenance Shop, Wagon Wash Facility, MV
Switchgear Room, Paint Shop, Security Control Room,
General Stores, Oil Laboratory, Compressor Room, Hostel
Building, 2 Deep Well Pumping Station, Mosque, Scrap Yard,
Wheel Shop, Bearing Shop, Signal & Telecommunication
Building, Domestic Wastewater Treatment Plant, Industrial
Wastewater Treatment Plant